Engineering Services Projects

Completed projects

All completed Projects since 2003 are tabulated below;

Year Client/Locations Description Project Details
2003 Mobitel (Pvt)Ltd Mobitel Battery Project Equipment transportation, technical site survey, charging and discharging testing, installation and commissioning of the battery banks covering entire Sri Lanka
2003 Etisalat Lanka Pvt Ltd (Sri Lanka) NEC MW installation of Tigo GSM network phase IV Equipment transportation, technical site survey, path survey, installation and commissioning of the MW (SDH and PDH) covering entire Sri Lanka
2004 Etisalat Lanka Pvt Ltd (Sri Lanka) NEC MW installation of Tigo GSM network phase V Equipment transportation, technical site survey, path survey, installation and commissioning of the MW (SDH and PDH) covering entire Sri Lanka
2005 Huawei Technologies Sri Lanka Pvt Ltd (Sri Lanka) Huawei – 2G DTL / 3G DTL / CDMA Suntel Installation of one 3G switch, 1 RNC and 30 no of Node B, 25 nos of CDMA base stations to Suntel and 2G MSC, BSC and 10 BTS in Dambulla / Anuradhapura Areas (Trial system)
2006 Dialog Axiata PLC (Sri Lanka) Dialog Telekom Greater Colombo fiber project Site Survey, testing of cable drums, splicing, testing, termination to ODF, rectification and commissioning
2006 Dialog Axiata PLC (Sri Lanka)Suntel Ltd Nera SDH – Long haul links Technical site survey, transportation of MW Radio equipments, installation, commissioning and integration of MW links andMUX’s including the Final Acceptance Tests
2006 Xian NEC Radio Communications Equipment Co Ltd (Sri Lanka) NEC MW installation of Tigo GSM network phase VI Equipment transportation, Technical site survey, path survey, installation and commissioning of the MW (SDH and PDH) covering entire Sri Lanka
2006 ZTE Lanka Pvt Ltd (Sri Lanka) ZTE BTS project for Tigo Installing and commissioning 450 of nos of ZTE BTS covering entire Sri Lanka. Installation of 1 MSC including power system and 10 BSCs including power systems
2007 ZTE corporation (Srilanka 2G system installation and commissioning Turnkey installation of MSC (1) BSC(10) and BTS (450)
2007 Alcatel Lucent Sri Lanka (Sri Lanka) Alcatel Lucent MW links and MUX project for Tigo Technical site survey, transportation of equipments, installation and commissioning MW links and MUX’s including the FAT
2007 Alcatel Lucent Sri Lanka (Sri Lanka) Alcatel Lucent BTS site survey / swapping project for Tigo Technical site survey and report, removal of ZTE BTS, installation of Alcatel BTS, commissioning and Technical   cut over (Within the given time period)
2007 Etisalat Lanka Pvt Ltd (Sri Lanka) NEC MW installation of Tigo GSM general expansion Technical site survey, transportation of MW radio equipments, installation and commissioning MW links. including the Final  Acceptance Test/s
2008 Dialog Axiata PLC (Sri Lanka) DTL site audit and asset tagging project Site survey, site equipment audit, Asset tagging for all passive and active equipment and provision of  tabulated data and detailed CAD drawings
2008 Dialog Axiata PLC (Sri Lanka) Nera SDH – Long haul links Technical site survey, transportation of MW radio equipments, installation, commissioning and integration of MW links and MUX’s including the Final Acceptance Test (FAT)
2008 Hutchison Telecommunications Lanka Pvt Ltd (Sri Lanka) NEC MW links and Muxes for HTLL phase I Technical site survey, transportation of MW radio equipments, installation, commissioning and integration of MW links and Muxes. Acceptance tests and test reports and management extending
2009 Hutchison Telecommunications Lanka Pvt Ltd (Sri Lanka) NEC MW links and Muxes for HTLL phase II Technical site survey, transportation of MW radio equipments, installation, commissioning and integration of MW links and MUX’s including the FAT
2010 Alcatel Lucent Sri Lanka (Sri Lanka) MW links and MUX project for Etisalat 3G phase Technical site survey, transportation of equipments, installation and commissioning MW links MUX’s including the FAT
2010 Alcatel Lucent Sri Lanka (Sri Lanka) Alcatel Lucent GSM / 3G site survey Technical site survey and reporting
2010 Alcatel Lucent Sri Lanka (Sri Lanka) Alcatel Lucent 2G / 3G BTS project for Etisalat 3G phase Technical site survey, transportation of equipments, installation and commissioning of BTS including the FAT
2010 Dhivehi Raajjeyge Gulhun PLC (Maldives) Dhiraagu Male Nera MW installation Transportation of MW radio equipments, installation, commissioning acceptance FAT  for 40 Nera PDH links covering the entire Maldives
2010 Etisalat Lanka Pvt Ltd (Sri Lanka) Etisalat MW relocation and dismantling for Etisalat Technical site survey, dismantling, transportation of equipments, installation and commissioning MW links MUX’s including the FAT
2011 Oman Telecommunications Company SAOG (Oman) MW Dismantling and installation for Oman Tel Technical site survey, dismantling, transportation of equipments, installation and commissioning MW links, including the FAT
2011 Ooredoo Maldives (Maldives) Wataniya Male SRAN installation Transportation of RAN equipments, installation, commissioning and FAT for 32 RAN sites covering the entire  Maldives
2011 ZTE Lanka Pvt Ltd (Sri Lanka) Mobitel stage 6 OSP interconnection project for Mobitel Technical site survey, installation, commissioning and testing of fiber interconnection between SLT and Mobitel sites including the FAT
2012 Dialog Axiata PLC (Sri Lanka) Dialog NMS project Survey, designing, implementation of NEC links including PAT/FAT
2012 Dialog Axiata PLC (Sri Lanka) DBN and DTL cabin interconnection fiber projects Site survey, excavation and duct laying, back filling and reinstatement, underground fiber cable laying, ODF installation and testing
2012 Hutchison Telecommunications Lanka Pvt Ltd (Sri Lanka) Huawei HTLL MW project Technical site survey, transportation of equipments, installation and commissioning of MW links, including PAT/FAT and relevant test reports
2012 Lanka Bell Ltd (Sri Lanka) Lanka Bell OSP projects Technical site survey, designing, approvals, (RDA / CMC / Police / PSD / Army), excavation and duct laying, back filling and reinstatement, underground fiber cable laying, ODF installation and testing
2012 Mobitel Pvt Ltd (Sri Lanka) In building solutions 2012 Survey, design, implementation and optimization of in-building solution/s. Submission of Designing report/s, PAT/FAT and submission of test reports
2012 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Fiber development work Excavation Laying of underground and overhead fiber cables, splicing and testing (Power and OTDR), Manhole installation, and back filling
2012 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – MSAN installation Technical site survey, implementation and PAT/FAT
2012 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Copper development work Excavation, Laying of underground and overhead copper cables and testing (Power), Manhole installation and backfilling
2012 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Peo Tv provisioning Site survey, implementation of Peo TV connections with all accessories
2012 ZTE Lanka Pvt Ltd (Sri Lanka) ZTE IBS projects 2012 Survey, designing, implementation and optimization of in-building solutions. Submission of Design reports including the FAT
2013 Mobitel Pvt Ltd (Sri Lanka) In building solutions 2013 Survey, design, implementation and optimization of in-building solution/s. Submission of Designing reports and test reports after FAT
2013 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – New connection provisioning Site survey, implementation of new connections including all accessories
2013 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Fiber development work Excavation, Laying of underground and overhead fiber cables, splicing and testing (Power and OTDR), Manhole installation and backfilling
2013 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – MSAN installation Technical site survey, implementation and PAT/FAT
2013 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Copper development work Excavation, Laying of underground and overhead copper cables and testing (Power), Manhole installation and backfilling
2013 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Peo Tv provisioning Site survey, implementation of Peo Tv including all accessories
2013 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2012 – Small scale development work Site survey, implementation of small scale development including all accessories
2014 Alcatel Lucent Sri Lanka (Sri Lanka) Network installation MW installation
2014 Alcatel Lucent Sri Lanka (Sri Lanka) 2G BTS installation Technical site survey, transportation of equipments, installation and commissioning of BTS ,Acceptance testing and submission of test reports
2014 Alcatel Lucent Sri Lanka (Sri Lanka) 3G BTS installation Technical site survey, transportation of equipments, installation and commissioning of BTS and acceptance test and submission of test reports
2014 Alcatel Lucent Sri Lanka (Sri Lanka) MW dismantling Dismantling and transportation of telecommunication equipments
2014 Mobitel Pvt Ltd (Sri Lanka) In building solutions 2014 Survey, design, implementation and optimization of in-building solution/s. Submission of Design reports and test reports after PAT/FAT
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – New connection provisioning Site survey, implementation of new connections including all accessories
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Fiber development work Excavation, Laying of underground and overhead fiber cables, splicing and testing (Power and OTDR), Manhole installation and backfilling
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – MSAN installation Technical site survey, implementation including the PAT/FAT
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Civil work Telecommunication related civil works
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Removal and relocation work Telecommunication related removals of infra-structure/s and relocation work
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Peo Tv provisioning Site survey, implementation of Peo TV connections including all accessories
2014 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Small scale development work Site survey, implementation of small scale development including all accessories
2014 Sri Lanka Telecom Services Ltd (Sri Lanka) Network cabling Network cabling installation
2014 Telecommunications Regulatory Commission of Sri Lanka (Sri Lanka) Supply, installation and commissioning of telecommunication antenna structure management system Executing all tasks from the understanding of  customer requirements users on the system/s
2014 TIA Investment LLC (United Arab Emirates) IBS design and validation Survey, design, validation and testing -Transmitter test/s
2015 Mobitel Pvt Ltd (Sri Lanka) In building solutions 2015 Survey, design, implementation and optimization of in-building solution/s. Submission of Design & Test Reports after PAT/FAT/td>
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2015 – New connection provisioning Site survey, implementation of new connections including all accessories
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2015 – Fiber development work Excavation, Laying of underground and overhead fiber cables, splicing and testing (Power and OTDR), Manhole installation and backfilling
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Removal and relocation work Telecommunication related removal and relocation works
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2015 – MSAN installation Technical site survey, implementation and testing
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2014 – Civil work Telecommunication related civil works
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2015 – Peo Tv provisioning Site survey, implementation of Peo TV connections including all accessories
2015 Sri Lanka Telecom PLC (Sri Lanka) OSP unit rate contract 2015 – Small scale development work Site survey, implementation of small scale development works

 

Ongoing projects

Client/Locations Description Project Details
Etisalat (Pvt)Ltd installation and commissioning of MW and BTS (2G/3G) Testing and Installation of BTS backup batteries at 411 sites
24X7 Fault attending islandwide
Dialog Telecom Drivetest Project 2G ,3G,Benchmarking According to the Dialog Scope 2G and 3G Drive testing Project in Colombo and Outstations
ZTE installation and commissioning of MW and BTS (2G/3G)  Transportation of equipment’s,  Installation, Commissioning of complete BTS, RF only BTS, swapping BTS, installation of TMA
Hutch installation and commissioning of MW systems Radio equipment’s, installation, commissioning and integration of MW links & MUXes. Acceptance tests and Test reports and Management extending.
Alcatel Srilanka installation and commissioning of MW /BTS/Multiplexror  Technical Site Survey, Transportation of equipment’s, installation and commissioning MW links & MUXes, Acceptance test and Test report.

 

Overseas projects

 

Client/Locations Description Project Details
 NSN – Qatar installation and commiissioning MW antennas 14 links installation withing the project
NSN – Qatar installation and commissioning of MW and BTS (LTE) Site survey/Material Delivery/Installation and Testing
NSN – Qatar Installation of Indoor Antenna system (IBS) Site survey/BOQ preparation/Installing and VSWR Testing
Huawei – UAE Walk test Testing of Indoor On-air sites to verify the signal quality and receiving levels
Nokia – UAE IBS Designing Test Transmitter test, Site survey and Designing the IBS system according to the customer/Operator requirements
Oman Tel – Oman Drive Testing and Optimization Testing of Outdoor 2G/3G/4G signal levels and give recommendation/s to improve their network
Maldives – MACL Installation of Airport Runner way Radar system Installation of LLZ/DVOR/GP systems and collaboration with Thales
Huawei – UAE IBS Designing Test Transmitter test, Site survey and Designing the IBS system according to the customer/Operator requirements
Peo TV/Wifi configurations Hand Core Drilling - IBS